MELROSE CONSERVATION COMMISSION
MINUTES OF September 2, 1999
[Approved 10/7/99]
Present: Robert Boisselle, William Dailey, Paul Locke, Bruce
Rider, David Valade
Minutes Approved
1. Voted: To accept the minutes dated 8/19/99 as amended.
Invoices
2. Voted to pay the following bills: Sony Transcriber for the Secretary's
use at $349.99 and $100 for the Secretary's services for the month of
August.
34 Crystal Street
3. Correspondence dated 8/20/99 was read from Denise Gaffey, Assistant
Director for Community Development. She did some checking on the status
of cleanup at 34 Crystal St. She was told that the cleanup is essentially
complete. The LSP is waiting on one more round of ground water sampling;
the first two rounds looked good so he is optimistic about the results
of the final test. It should be scheduled in about one month after which
time he will issue the Response Action Outcome Report and solicit public
comment. The DEP Tracking Number is 3-0017418.
121/129 Penny Way
4. Correspondence was read from John Colucci, representative of the
Adams Penny
Realty Trust, which has purchased a seven (7) lot subdivison located
on Penny Way, Melrose. The name, address and telephone number of the
project supervisor is Brian Butler, 7 Cypress Park, Melrose; Tele. (781)665-1951;
Cell Phone (617)605-6656; Pager (617)473-8585.
Correspondence was also read from Brian Butler, introducing himself
as project supervisor. He requested an on site meeting with the commission
as soon as possible to review the proposed work to date. He has marked
out limits of work and set up hay bales and silt fences as the conservation
OOC indicate. He would like to meet as soon as possible as he has land
clearing equipment tentatively lined up to begin on Tuesday, 8/24/99.
He requests that this letter serve as a 24 hour notice to the MCC to
begin construction activities on site.
David spoke with Mr. Butler and he then visited the site. They had
25 hay bales across from the actual site and everything looked fine
so he knocked on the door and told the owner to go ahead with the project.
CONFERENCE/TRAININGS AVAILABLE
5. The MACC Fall program/bulletin lists Conferences to be held on 10/23
at the Northeastern University in Burlington, and also on 11/20 at the
Quality Inn in Pittsfield. Any commissioners attending the meeting will
be sponsored. There is an Evironmental U Mass Ext. - intensive training
workshop 11/21. The Certification Courses of the MAPT Training Program
are from 9/25 - 11/13. Any commission members taking these courses will
be reimbursed.
10 Windsor Street
6. Nothing has come in from the DEP regarding a number for 10 Windsor
St., therefore an OOC will not be issued at this time. It will probably
be done at out next meeting.
3 Maple Terrace
7. We have a NOI from 3 Maple Terrace, Anthony and Adella Dantona,
concerning the installation of a 35 ft. 6 in. x 15 ft. 6 in. inground
pool and retaining wall with minor regrading near a bordering vegetated
wetland. The hearing will be scheduled for our next session which will
be 8/16 at 7:45 p.m.
Granite & Burnett Street
8. David went by Granite & Burnett Street and it appears that everything
is cleared up although there is a lot of vegetation there now where
they cleared the area.
9 Bow Street
9. Bob received a call from the owner at 9 Bow St. It seems that Mr.
Drago, the contractor, is getting ready to put a drain in their backyard
and hook up to one of the sewer lines. Bob informed her to read the
OOC and the original grading operation is for that nothing is to be
touched and it should come before us at the next go around of that property.
She was under the impression that she could do that right away and she
was redirected by the Inspection Services at City Hall, indicating that
it is a flood area that she is in and she should be coming before us
for any construction in the area. She wasn't aware of that and he was
getting ready to put the draining and piping in. Bob told her to reconsider
that because her neighbors may have problems and the city may have a
problem if they hook into any of their lines without their permission.
She indicated she was coming to the meeting tonight, but she is not
here.
Towners Pond Bridge
10. A work crew from the commission plans to meet this Saturday, 9/4
at 10 a.m. to rebuild the disassembled bridge at Towners Pond. Bob has
secured some power tools to use.
11. It was voted to adjourn at 7:45 p.m.
Respectfully submitted,
Nancy Pritchard
Commission Secretary
|