Meeting Minutes of Thursday,
June 20, 2002
Present:
Sean Kealey, Paul Locke, Susan Murphy and Nancy Naslas.
The meeting came to order at 7:40 p.m.
Mt. Hood Restoration Project--Parks Commission
Charles Fuller and Mike Interbartolo with
the Parks Commission were present at this meeting.
Charles Fuller passed out a monthly progress report,
and then proceeded to give the commission an update.
Charles:
The schedule calls for the seeding and sodding to be
accomplished in September and October and to basically have
the course rapped up by late November.
There will be a two-week period the following April to
take care of any things that may have been affected by winter
weather. So,
basically, it should be rapped up but not ready to play on in
November but, hopefully, in April it will be ready to play on.
Mr. Fuller mentioned that they have been getting a lot
of positive feedback from the golfers, and that the golfers
come by and take a look at what has been done and check out
what is going on.
Mr. Fuller told the commission that the
contractors are ahead of schedule and gave the commission some
statistics. The
removal of the peat from below the fairway (Mr. Fuller passed
out photos) as of June 5th, they were 80-90% complete with the
peat removal. They
had to suspend it for a short time because of wet weather
conditions on the lower part of the field because once it gets
wet, it stays wet. Hopefully,
it will stay dry tonight which I think it is supposed to and
will go back and resume peat removal tomorrow, the 21st,
and the schedule calls for the peat to be removed between the
10th and the 20th of June and it is now
the 20th. Basically,
I think we are ahead of schedule on that.
The cut on the 12th fairway is
more than 50% complete and that was scheduled to of taken
place between June 26th and July 22nd.
So, we haven’t even reached the start date on that
and they are more than half-done in my opinion.
The fairway slope that is the upper field, which will
not be used for golfing, is going to be finished.
I call this the plateau, but it is up higher than the
12th fairway into the east of it and that is about 60-70%
complete. This was
scheduled to be done during the period of June 3rd
- 28th. So,
you could say that is probably just about on schedule.
The two wetlands that work will be done
in on the north and south are going to be done during the late
summer/early fall and these are not major parts of the
project. The major
ones are the ones that they jumped in on.
The peat removal is probably the most difficult part of
the job because in places they have to dig down 18 to 20 feet
below the other fairway grade to get the peat out, and you
couldn’t dig an area much bigger than half of the size of
this room at any given time because of failure.
If you look at the pictures, you can see
the cracks and the big dig fill that was put in as they were
digging down to take the peat out.
This material would crack and open up, and in one case,
on one day it actually moved four feet out while working with
the equipment. Taking
the peat out is a two-stage operation.
It takes a small backhoe to actually dig down, pick it
up, put it on the plateau and then the backhoe would pick it
up from there and turn it around and load the truck with three
bucket fulls. Then
if the truck were lucky, it could make it up the very steep
grass to the top to take it up.
The peat is being dried in what would have been the
baseball/soccer field area up closer to the top.
Yesterday, the first sample mix of peat
and sand that have been run by the people that were going to
make the topsoil was submitted.
The sample went to the lab, and we will be hearing back
from them early next week on the combination.
Early indications show that it is going to be peat and
sand, and the big dig fill does not work well with this mix.
It is just too clayey.
Instead of trying to mix it with the top soil, we would
be better off putting down four inches of big dig fill as an
underlayer, and I would only do it in places other than the
golf course and that is just my opinion.
The plan calls for removal of rock next
to the 12th green, to the left of the 12th
green, and this is a spot that can take up quite some time
because it shows that ledge got buried in big dig fill.
When I saw it, I thought we might be lucky and be able
to dig down and work around it and not have to remove the
ledge.
Nancy:
Are you planning on relocating the drainage pipe over
to account for that a little?
Charles:
No, this is near the green.
This is where we have the plateau of fairway slope
pitching down and delivering water down towards the green, and
by taking the ledge out, allows the cart path to be turned
away from the green. The
golf course architect wanted 30 feet minimum from the ledge of
the green to the cart path, and on the present course, there
is about 20 feet. Basically,
it looks to me like we can get 25 feet without taking the
ledge out. We will
know tomorrow if it is going to be 25 or 30 feet, but this
golf course architect did agree that whatever we could give
him, he would go along with it. So, I would say in the range
of 25 feet plus from the edge of the cart path and the other
side of the green. I
think that most of the leading situation here is that we
prevail the ledge. It
is actually going to convey the waterfall on down and it will
spill over the ledge and come down into a trench just before
you get to the green and it will be rather picturesque when
formed.
Nancy:
Will you have the water cascading over that area?
Charles:
Yes, it will come and wash over the rock, and the rock
would be visible to anybody going by.
Nancy:
Now, that area you’re talking about is adjacent to
the new replication area?
Charles:
It is on the other side of the fairway, left side on
the green. The
replication area is on the right.
Nancy:
I thought we changed the replication area?
Plans were than taken out and put on the
table for everyone’s review.
Charles Fuller explained the plans.
This is the tee and this is the grade.
This is stone wall facing number two.
This is a rather flat plateau where we are looking.
Water will come down here and then actually tumble out
back here because this is significant ledge.
Nancy:
The first thing I mentioned was this the location of
this pipe.
Charles:
Right.
Nancy:
You were going to move it over this way a little.
Charles:
We talked about this yesterday.
We may relocate it, but we don’t know yet.
There will be a manhole rather than putting into this
basin which is how it is shown here.
I was trying to avoid putting a manhole in the cart
path, but I will work out the details on that.
Nancy:
On this wetlands replication area, is that the one you
said was already a wetland?
Charles:
Yes, and we are considering another area, and I must
admit the elevation wise.
Nancy:
I thought the area that you were suggesting was over
here next to this.
Charles:
This is the proposed replication area.
I was proposing something in here.
Nancy:
Okay.
Charles:
I have measurements of the concrete wall.
I established that the contour of the wall was just
about at 134 here. However,
when I went over here a couple of days later and looked, this
was dry and even down less than 133.
Now granted, there have been some dry days in between,
but I think what has happened is there has been sediment into
this area. I think
what has happened now is more flow goes into the wetlands here
and makes it way down than might have originally gone through
here and that is why I suggested that this be an area that be
worthy of consideration for replication because there is much
less material in here.
Nancy:
This is the way you submitted it to us two weeks ago at
our meeting with a memo and this is what we, the commission,
voted on approving. We
do appreciate the fact that you brought it to our attention
that the original wetlands delineation was, if not incorrect,
it wouldn’t change since it wasn’t specific originally
delineated. So, it
did make more sense to move it, and we concurred and it is in
our minutes. So,
you have the go ahead on that change and at the time our
understanding was that this was going to be the replacement
replication area. I
think that this is going to be part of the work that you were
already going to be performing oversight on.
We didn’t require any submittals or amendment to our
NOI’s. That was
our official response.
Nancy:
I will send Mike and Charles our minutes just so you
have the official record that it has been changed and been
approved. That was
the only change that we have officially approved so far.
The other question is what about the concrete blocks?
Are those gone now?
Charles:
I was just going to talk about.
We came up with the result of the grade and this has
been taken place along the lower parts of the fairway.
A couple of people are concerned about the treatment of
the slope. It
seems very steep for a golfer or anybody else.
It is a long stretch down.
It is going to be tough.
I think it was Rick who came up with the suggestion
about the concrete blocks.
He asked me what was going to happen to the concrete
blocks out there, and he told me that they were to be removed.
Paul:
Is that what the contract calls for?
Charles:
When Rick was talking about picking the grade up off of
the bottom of the slope, and thought that if we had some
boulders or something that they would help.
Then Rick thought of these blocks and mentioned to add
the concrete blocks there.
I counted and there are 40 blocks that are protecting
this area on top of another 40.
This would give you 240 feet, and if you were to move
just the top course off here and put it into two courses over
here, you would each would have about 120 feet of block that
would allow us to flatten up the hill.
Mike:
I think the concern on those walls is that there is
really no footing under those concrete walls and that is why
they are tilting.
Charles:
Yes, they would have to supported.
There is no footing under the concrete blocks.
This is not a wetlands area.
Mike:
Do you remember the first time you were out with Colin?
The contractor was proposing that we use the wall as
the starting point of the slope back.
Nancy:
Right.
Mike:
They were concerned about that.
What they suggested was that we could remove the top
course on the high part and then filing over the wall.
Leaving the wall in place because the wall is not in
the wetlands area. It
is just holding back the water and the fill line is actually
at times anywhere four to eight to ten feet beyond the wall.
So, that is what the suggestion was.
Why take them out if we can fill in both sides.
I told him we would have to check with the Conservation
Commission.
Nancy:
But as of now, none of your final grades as submitted
in your NOI have been changed.
Mike:
That is correct.
Nancy:
Okay. As
far as leaving some of those concrete blocks underground -
Mike:
It won’t change the grade.
Nancy:
They would just be underground.
Mike:
Charlie is talking about building the wall up.
Would that change the grade?
Charlie:
It would be up the hill more.
It is more between 160 and 180.
Mike:
We ask that the commission consider us leaving the
blocks in place and filling in and around them without
changing the proposed grades of the wetlands.
Nancy:
However many you leave in the resulting final grade
will still be the same as submitted in the Notice of Intent?
Mike:
Right.
Nancy:
There would just be concrete blocks underground.
Mike:
Instead of it being fill, it would be concrete blocks.
As we study it, if it would decide to raise the
elevation away from the wetlands, than we will come back and
talk to you.
Nancy:
So, it is cheaper to leave them in there than to try to
move them.
Mike:
Right. Because
what it calls for by removing them would require stockpiling
them back up by the tower and then you would have to transport
them up.
Nancy:
Well, any opinions from the commissioners for leaving
very large concrete blocks in place underground?
Mike:
They are about two feet by two feet by six feet long.
Nancy:
They were used as a temporary measure to stop the till
of the slope from slumping farther into the wetlands.
They built a big long wall.
Mike:
To keep the water from penetrating.
Sean:
Are there any reasons for water flow why it would be
better off not there?
Nancy:
The water doesn’t go that way.
Nancy:
Is that a motion to make it official?
Paul:
I move to request that the concrete blocks remain in
place as long as it doesn’t effect the final grades on the
slopes.
Susan:
Second
Nancy:
I move and seconded it, all in favor, aye.
So, that is fine that will be a part of our minutes.
Mike:
Colin Duncan will be at the next job meeting on Monday.
I will be telling him the construction schedule and
will ask him to mark up where and how the testing should take
place.
Nancy:
I am sorry I haven’t returned the schedule.
It looks like such a daunting task.
Our concerns are more like any changes and to know
about them in advance.
Mike:
That is why I asked him to do it so we would have a
heads up rather than get ahead of it and find out we should
have done it.
Nancy:
It is not until you get the whole area stabilized
before you could even start cleaning up the wetlands.
I think we can just have a monthly visit like this.
Mike: That
is part of Charlie’s contract that he has to attend a
monthly meeting of the Parks Commission and Conservation
Commission.
Nancy:
Good. I am
also going to give you the list of our commissioners.
Mike:
Has the commission gone out and reviewed the wetlands
protection?
Nancy:
I don’t think so.
I think just for the fact that we were just notified.
Mike:
It is really shaping up very well, and they are
pleased.
Nancy:
A list of commissioners was passed out to Mike.
Just to let you know, if you can’t reach me, Paul
usually fills in for co-chair.
I don’t know if you have anything else Mr. Fuller
that you would like to through formally?
Charlie:
I think that was basically it.
Just to give you an idea where the schedules are and to
give you an update.
Nancy:
Then there is the environmental scientist from Allan
& Major. What
are her qualifications? Now,
what is the difference between what she is doing verses what
Colin Duncan is doing?
Mike:
Colin Duncan will only review their findings.
Colin Duncan is not going to do any testing.
Nancy:
Okay.
Mike:
That is the contractor’s wetlands scientist, and by
contract, he is required to do any and all testing required.
Nancy:
So, Ms. Granisa is going to be in charge of oversight
or managing the wetlands replication work as well as the
wetlands remediation work, and Colin Duncan will be in charge
of oversight and review. Okay.
Do the commissioners have any other questions?
Nancy asked Mr. Fuller for a phone number in case
someone comes up. Mike
stated that there is a trailer with power.
The clubhouse number is 781-662-5888.
Mr. Fuller gave his cell phone number.
It is 781-389-6085.
It was also mentioned that the heavy equipment is out
of there by 3:30 p.m.
Nancy:
Any more questions?
Thanks for coming.
Charles Fuller and Mike Interbartolo left at 8 p.m.
Meeting Minutes
It was stated that there were two sets of
minutes outstanding, May 16th and June 6th.
A motion was made to approve those minutes as finalized
by e-mail. Paul
moved to accept those minutes, and Susan approved them too.
Nancy stated that she reviewed them closely and edited
them. Moved
and seconded, all in favor, aye.
The minutes of May 16th and June 6th
are approved.
Budget
Nancy went to the budget meeting on June
19th with the Board of Alderman and the Appropriations
Committee. The
original budget, which was in excess of
$42,000 possibly more, and the mayor’s budget, which
is our edited budget, was sent to the alderman at $24,095.
Basically, what he did was knock our maintenance line
items back down to what is was this year.
So, the guardrails and the tree removal and things like
that probably got knocked off, but he didn’t specify what
got knocked off in maintenance.
We have a $15,000 worth of maintenance money to spend
in fiscal year 2003, 7% less than last year but it was
approved by the Board of Alderman.
Also, regarding this fiscal year, at least what is left
of this month, fiscal year 2002 budget, we still have about
$14,000 to spend of this year’s budget.
Keeping in mind that our ponds work on a growing
season’s calendar and not a fiscal calendar, and that work
has been started this month and that we have encumbered the
money to be carried over.
I did that with the auditor.
So, the work on Ell Pond, Towners Pond and Swains Pond
will be started this month and will be continued into the
summer.
Mail
Nancy handed out personal mail to each
commissioner. It
was a dedication notice for the new park on Crystal Street
prior to the Ell Pond festival.
Please try to attend this Saturday, June 22nd at 5 p.m.
for the dedication and the Ell Pond festival at 5:30 p.m.
Invoices
Invoices from our former secretary, Nancy
Pritchard. The
month of May 2002 in the amount of $366.92 and the month of
June 2002 in the amount of $135.00.
Motion to approve these -- Paul approved, Susan
seconded, all in favor, aye.
We have also received a bill, which I
received back from Mike Hughes.
It is the bill for the total control hydrocarbon
analyses that we ran on the soil near Conant Park.
They decided that we have enough money in our
professional services budget to pay it.
After I kindly volunteered to take the samples for him
for free if he would pay for them, he sent the bill back.
I decided that we do have the money in our fiscal year
2002 budget to pay for them so I think I will just pay for
them if it is all right with the rest of you.
I propose that we pay it.
Do I have a motion?
Sean motioned to pay them, Susan seconded.
It is $240. They
were taken from adjacent to some abandoned 55-gallon drums
that are either in a wetland or just immediately adjacent to a
wetland of Spot Pond Brook down stream from Conant Park.
Paul:
Have they done any further work on it?
Nancy:
I don’t know. I
haven’t heard of any, and I do know the neighbor so he will
tell me if anything happens.
Sean:
When is their 120 days?
Nancy:
May 15th is when it is stamped received.
I will speak to Mr. Hughes again.
Nancy:
The chemist interpreted the results for unknown
hydrocarbon. They
called it naturally occurring paraffin.
But, nevertheless, it is a TPH test with a TPH RESULT.
It does need to continue on down the DEP requirement.
Okay. Do we
have a motion to pay this bill for $240?
Paul approved, Susan seconded, all, aye.
Hickory Street
Nancy:
We have received a Request for Determination of
Applicability for Hickory Street in Melrose. They are on the
agenda for a public hearing on Thursday, July 18th at
7:30 p.m. I
suggest that before July 18th, we go take a look up
there and decide if we need to have a wetlands scientist check
out the property because the applicant has not or if we think
that a wetlands scientist should review the property.
It was asked if Hickory Street was currently a paper
street? Nancy
responded that she thought so and believed that it was very
steep and hilly. Nancy
asked Paul to coordinate a site meeting and that Nancy would
put the ad in the paper. Nancy
has the original signed RDA, and she will start a file.
That is all I have.
Does anyone else have any other matters?
Should we open our meeting for any public comment?
No further comments.
Voted:
Meeting adjourned at 8:15 p.m.
Respectfully submitted,
Meredith L. Beauchesne, Conservation
Secretary