I have a permit but there has been a change of plans. What do I do?

Submit a request in writing that includes a brief narrative about your change to the Conservation Commission. The change will be placed on the Commission’s next agenda. The Commission will then vote whether the change is one of the following:

  • The change is de minimus. This means the Commission will not need to add extra conditions to your Order of Conditions.
  • The change will require amending the Order of Conditions. This means that the Commission will need to add additional conditions to your Order of Conditions. The change will need to be advertised and abutters will need to be notified.
  • The change is so significant that the Commission would like the work to be submitted as a new Notice of Intent.